Messerschmitt
Guest
I wanted to have a confirmation.. .
when carpentry structures arrive at the construction site (e.g. welded ipe beams, built h beams and piolate), the director of the works must check that they are present:
- in the ddt: the registration number with which the processing center, which produced the carpentry, is recorded at the central technical service, in addition to the name or logo of the same center.
- a document with which the technical director of the plant certifies that the checks required by ntc 2008 on the carpentry in question have been carried out.
to issue the latter certificate the technical director of the processing center must have carried out at least 3 tests for each supply from a qualified external laboratory on heels taken from the processed material, to verify that the processing did not alter the characteristics of the basic material.
the director of the works, in addition to the certificate of execution of these tests made by the technical director, can ask to see also the results of these tests.
with supply means a group of carpenters of the same type, which have the same nominal dimensions. If, for example, I have 4 different types of beams built (different by section and length) then I have to consider them as distinct supplies and each will want its tests and its certificate of execution controls.Is it more or less correct as I wrote?
when carpentry structures arrive at the construction site (e.g. welded ipe beams, built h beams and piolate), the director of the works must check that they are present:
- in the ddt: the registration number with which the processing center, which produced the carpentry, is recorded at the central technical service, in addition to the name or logo of the same center.
- a document with which the technical director of the plant certifies that the checks required by ntc 2008 on the carpentry in question have been carried out.
to issue the latter certificate the technical director of the processing center must have carried out at least 3 tests for each supply from a qualified external laboratory on heels taken from the processed material, to verify that the processing did not alter the characteristics of the basic material.
the director of the works, in addition to the certificate of execution of these tests made by the technical director, can ask to see also the results of these tests.
with supply means a group of carpenters of the same type, which have the same nominal dimensions. If, for example, I have 4 different types of beams built (different by section and length) then I have to consider them as distinct supplies and each will want its tests and its certificate of execution controls.Is it more or less correct as I wrote?