• This forum is the machine-generated translation of www.cad3d.it/forum1 - the Italian design community. Several terms are not translated correctly.

schema dm 11.04.11 - verifiche periodiche

  • Thread starter Thread starter gerod
  • Start date Start date
Bye-bye
it seems like a great job: I would only mention that for the first verification we are not talking about the equipment under pressure, for which it continues to apply what is indicated in dm329/04 (in fact, while what is indicated part of the complaint of commissioning, for pressure vessels could be required to ininathe a prior verification, even before the commissioning, in which case the complaint is made but the request for verification). for subsequent checks instead is correct.
just to be pointy.
Hi.
 
I did an update (I don't know if you saw it, rev 01... the link is the same).
the rev explains some things that remain as first plant verification, homologation, etc.
Try to give an eye!
Hello and thank you
 