bigsnake
Guest
Hello everyone!!! ! ! !
I have just recorded but I have already read many discussions that have been very helpful, so to start I wanted to congratulate all the participants of the forum.
I use proe wf4 or in some cases old 2001, but in both I noticed something particularly annoying
I give you an example: I have an assembly of about 20 components, of which one of more than 1000 features, say 1500, called "tassello"
I do automatic regeneration and it's okay.
during the regeneration known that the rigen of the "tassello" component starts from feature 1300.
I continue my project by adding features to all other components, completely untied by dowel, without interfering with previous features.
I do automatic regeneration and maybe now I start with feature 400!! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !
In addition to a huge waste of time, sometimes it happens that I have some incomprehensible failure, which is even worse.
How can I solve or circumvent this situation?
is possible, arrived at a certain point of the project, "block it" so as to decide independently when to start automatic regeneration?
thanks to all in advance
I have just recorded but I have already read many discussions that have been very helpful, so to start I wanted to congratulate all the participants of the forum.
I use proe wf4 or in some cases old 2001, but in both I noticed something particularly annoying
I give you an example: I have an assembly of about 20 components, of which one of more than 1000 features, say 1500, called "tassello"
I do automatic regeneration and it's okay.
during the regeneration known that the rigen of the "tassello" component starts from feature 1300.
I continue my project by adding features to all other components, completely untied by dowel, without interfering with previous features.
I do automatic regeneration and maybe now I start with feature 400!! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !
In addition to a huge waste of time, sometimes it happens that I have some incomprehensible failure, which is even worse.
How can I solve or circumvent this situation?
is possible, arrived at a certain point of the project, "block it" so as to decide independently when to start automatic regeneration?
thanks to all in advance